1) Export project file as Primavera PM – (XER) and Layout File (PLF). Share the XER and PLF files with the commentator\updater.
2) Load the exported XER file PLF into excel by using NEO-Project Toolbox. This will open XER file in excel with the layout.
3) After the last column open 3 new column for Expected/Actual Start, Expected/Actual Finish, Comments
4) Save the excel file. You can record their input\feedback into the new opened columns and send back to scheduler for updating the P6 schedule. If there is a delay\shift at the starting or finishing timing of the activities at one of the activities, the delay\shift reason can record in comments column. That information can be used at the schedule update narrative.
5) When you right click on the Activity Name Column, the commentator\updater can see the activity relationship or activity calendar. With this way you can review in detail, make comments and\or change request on relationship and calendar.
1) Does everybody need NEO-Project Toolbox add-in for this methodology?
Yes, all commentators\updaters need NEO-Project Toolbox add-in to proceed with this methodology.
2) Do commentator\updater need to reload XER files?
NEO-Project toolbox stores the original XER data next time you can directly open the XER at the pull-down menu in the NEO-Project Toolbox add-in tab.
3) Can we filter out based on the commentator\updater?
You can ask your scheduler to create a specific layout for specific tasks, groups, or persons such as structural works, design, etc. With the XER file if you choose the specific Layout File (PLF) you can only see those activities and proceed with this methodology.
4) Can we use different Layout Files (PLF)?
With one XER file, you can use different Layout (PLF) files easily using pull-down menus at the NEO-Project toolbox add-in tab.
Method # 1 1) Copy List of activities from P6 into Excel. Select all activities in P6 (Ctrl+A), copy activities (Ctrl+C) 2) Open excel and paste the copied data in excel. Select cell A1, Paste (Ctrl+V) 3) From NEO-Project tab in excel choose Paste-Organize. This will organize, level and colored the pasted data. 4) After…
Create a Free Account Beginner’s Guide to Construction Project Management According to the Project Management Institute (PMI), project management is “the art of directing and coordinating human and material resources throughout the life of a project by using modern management techniques to achieve predetermined objectives of scope, cost, time, quality, and participating objectives.” Project management…
Discover Our Toolbox The construction industry has been one of the slowest moving industries to get into technology. Most things were done by pen and paper which leads to a disconnect between the field and the office. This can be confusing and often leaves a feeling of disorganization. Oracle Primavera has done a great job…
NEO International Inc.
1000 Innovation Dr. Suite 500,
Kanata, ON K2K 3E7 – Canada
email: info@neo-project.app
© 2020 Neo International Inc. All rights reserved.